● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Environment

Iron ore underground mine: Noise and vibration — solution & design basis

Noise limits at the site boundary are exceeded — a 140 t/h design basis, configuration and acceptance checks.

Iron ore underground mine with noise and vibration is normally resolved by checking the circuit against the saleable product specification first: isolate screen and crusher mounts and maintain them. For a 140 t/h design point on iron ore, HAMAC would review jaw / gyratory → cone → screen → magnetic separation, then confirm the settings with a written acceptance test. The answer depends on the mass balance, not on a catalogue capacity figure.

140 t/hindicative design point
80–250 MPacompressive strength
100–250 t/hscenario capacity band
340 kWorder-of-magnitude installed power
Key takeaways
  1. Iron ore is medium–high in abrasiveness and medium in moisture sensitivity; High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit.
  2. For underground mine the priority is compact footprint, constrained by restricted headroom, ventilation and haulage access.
  3. Noise and vibration typically appears as: noise limits at the site boundary are exceeded.
  4. First corrective action: isolate screen and crusher mounts and maintain them.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for iron ore underground mine

The design basis starts with the rock, not the machine. Iron ore is rated at 80–250 MPa compressive strength with medium–high abrasiveness, medium moisture sensitivity and a loose bulk density around 2.10 t/m³. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. A change in one stage changes the circulating load in all the others.

A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 140 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of −10 mm fines and sized lump ore.

Iron ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialIron ore · 80–250 MPa · abrasion medium–high
Design throughput140 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~400 mm
Target product−10 mm fines and sized lump ore
Loose bulk density2.10 t/m³
Suggested circuitjaw / gyratory → cone → screen → magnetic separation
Iron ore underground mine — Design basis for iron ore underground mine — HAMAC crushing and screening equipment
Iron ore underground mine — Design basis for iron ore underground mine — HAMAC crushing and screening equipment reference.

Why noise and vibration appears in this circuit

Noise limits at the site boundary are exceeded. In a iron ore underground mine this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.

  • the crusher and screen are mounted without adequate isolation
  • the plant is arranged with its loudest face toward the boundary
  • worn bearings and loose liners add impact noise

Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) measure boundary noise at the worst-case operating state; 2) log vibration on screen bearings; 3) inspect isolation mounts during planned stops. HAMAC states nominal values alongside the conditions they were measured under.

Recommended equipment configuration

For iron ore at 140 t/h the working train is jaw / gyratory → cone → screen → magnetic separation. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for iron ore and for a softer rock. A change in one stage changes the circulating load in all the others.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~175 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~42 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 60% circulating load
ConveyingBelts sized for fresh feed + return stream, 2.10 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 340 kW order-of-magnitude connected load

The corrective actions for noise and vibration are applied on top of this base circuit: isolate screen and crusher mounts and maintain them; orient the plant and use stockpiles as acoustic barriers; replace worn bearings and re-torque liner fasteners.

Iron ore underground mine — Recommended equipment configuration — HAMAC crushing and screening equipment
Iron ore underground mine — Recommended equipment configuration — HAMAC crushing and screening equipment reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 60% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.

  • Measure boundary noise at the worst-case operating state
  • Log vibration on screen bearings
  • Inspect isolation mounts during planned stops
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 140 t/h nominal
GradingFull sieve analysis, agreed standard, −10 mm fines and sized lump ore
Crusher settingCSS measured and logged, ~42 mm starting point
PowerMain-drive current at steady feed, 340 kW connected load
WearLiner mass before and after, cost per saleable tonne

HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for iron ore, while compact footprint determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.

  • Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 140 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

A change in one stage changes the circulating load in all the others. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Iron ore underground mine — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment
Iron ore underground mine — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment reference.
FAQ

Iron ore underground mine — questions answered

Direct answers to the questions buyers ask most often.

What causes noise and vibration in a iron ore underground mine?

Noise limits at the site boundary are exceeded. The usual causes are the crusher and screen are mounted without adequate isolation; the plant is arranged with its loudest face toward the boundary; worn bearings and loose liners add impact noise. isolate screen and crusher mounts and maintain them.

Which crusher train suits iron ore at 100–250 t/h?

A typical configuration is jaw / gyratory → cone → screen → magnetic separation. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 140 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call