Design basis for granite arid desert site
The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Measurements are only comparable when the sieve standard is the same.
A arid desert site must control dust with very little water available, constrained by extreme heat, abrasive airborne dust and limited water. The commercial priority is dry dust extraction. For this combination HAMAC works from an indicative design point of 200 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Granite · 100–250 MPa · abrasion medium–high |
| Design throughput | 200 t/h saleable product (150–350 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | 0–5, 5–10, 10–20, 20–40 mm |
| Loose bulk density | 1.45 t/m³ |
| Suggested circuit | jaw → cone → cone / VSI → 3-deck screen |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a granite arid desert site this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For granite at 200 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~250 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~34 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.45 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 590 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 70% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 200 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm |
| Crusher setting | CSS measured and logged, ~34 mm starting point |
| Power | Main-drive current at steady feed, 590 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while dry dust extraction determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 200 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.