Design basis for dolomite high-altitude site
The design basis starts with the rock, not the machine. Dolomite is rated at 60–180 MPa compressive strength with low–medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.42 t/m³. Suits impact crushing and downstream grinding; the fines fraction is often the most valuable product. A change in one stage changes the circulating load in all the others.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of aggregate, agricultural lime, filler powder.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · 60–180 MPa · abrasion low–medium |
| Design throughput | 150 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~650 mm |
| Target product | aggregate, agricultural lime, filler powder |
| Loose bulk density | 1.42 t/m³ |
| Suggested circuit | impact crusher → screen → optional Raymond mill |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a dolomite high-altitude site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For dolomite at 150 t/h the working train is impact crusher → screen → optional Raymond mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for dolomite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.42 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 410 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 70% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, aggregate, agricultural lime, filler powder |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 410 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for dolomite, while drive and cooling margins determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.