● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Material solutions

Construction & demolition waste remote site: Clay contamination — solution & design basis

Screens blind and the chamber packs during wet weather — a 90 t/h design basis, configuration and acceptance checks.

Construction & demolition waste remote site with clay contamination is normally resolved by checking the circuit against the saleable product specification first: scalp clay at the grizzly before primary crushing. For a 90 t/h design point on construction & demolition waste, HAMAC would review mobile impact + magnet + picking → screen, then confirm the settings with a written acceptance test. Written acceptance criteria prevent a dispute turning into a redesign.

90 t/hindicative design point
variablecompressive strength
60–180 t/hscenario capacity band
200 kWorder-of-magnitude installed power
Key takeaways
  1. Construction & demolition waste is variable in abrasiveness and variable in moisture sensitivity; Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone.
  2. For remote site the priority is energy and spares autonomy, constrained by diesel generation and infrequent service visits.
  3. Clay contamination typically appears as: screens blind and the chamber packs during wet weather.
  4. First corrective action: scalp clay at the grizzly before primary crushing.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for construction & demolition waste remote site

The design basis starts with the rock, not the machine. Construction & demolition waste is rated at variable compressive strength with variable abrasiveness, variable moisture sensitivity and a loose bulk density around 1.20 t/m³. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. The reference conditions should be attached to every figure quoted.

A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 90 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 0–4, 4–20, 20–40 mm recycled aggregate.

Construction & demolition waste — design basis (nominal values)
ParameterIndicative value / method
Raw materialConstruction & demolition waste · variable · abrasion variable
Design throughput90 t/h saleable product (60–180 t/h scenario band)
Maximum feed size~350 mm
Target product0–4, 4–20, 20–40 mm recycled aggregate
Loose bulk density1.20 t/m³
Suggested circuitmobile impact + magnet + picking → screen
Construction & demolition waste remote site — Design basis for construction & demolition waste remote site — HAMAC vibrating screen
Construction & demolition waste remote site — Design basis for construction & demolition waste remote site — HAMAC vibrating screen reference.

Why clay contamination appears in this circuit

Screens blind and the chamber packs during wet weather. In a construction & demolition waste remote site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.

  • clay-bearing overburden enters with the shot rock
  • spray water is added without a washing circuit
  • transfer chutes are too narrow for sticky material

Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) measure surface moisture at the shift level; 2) inspect deck open area after each wet shift; 3) log the pressure drop across dust collection. A signed settings log at handover protects both parties later.

Recommended equipment configuration

For construction & demolition waste at 90 t/h the working train is mobile impact + magnet + picking → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for construction & demolition waste and for a softer rock. The reference conditions should be attached to every figure quoted.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~113 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~22 mm at the secondary stage
Secondary / tertiaryscreen
ScreeningMulti-deck screen sized for 50% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.20 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 200 kW order-of-magnitude connected load

The corrective actions for clay contamination are applied on top of this base circuit: scalp clay at the grizzly before primary crushing; choose rubber or polyurethane media with ball trays; add a washing stage with water recovery where the specification allows.

Construction & demolition waste remote site — Recommended equipment configuration — HAMAC vibrating screen
Construction & demolition waste remote site — Recommended equipment configuration — HAMAC vibrating screen reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 50% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.

  • Measure surface moisture at the shift level
  • Inspect deck open area after each wet shift
  • Log the pressure drop across dust collection
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 90 t/h nominal
GradingFull sieve analysis, agreed standard, 0–4, 4–20, 20–40 mm recycled aggregate
Crusher settingCSS measured and logged, ~22 mm starting point
PowerMain-drive current at steady feed, 200 kW connected load
WearLiner mass before and after, cost per saleable tonne

A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for construction & demolition waste, while energy and spares autonomy determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.

  • Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 90 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

The reference conditions should be attached to every figure quoted. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

FAQ

Construction & demolition waste remote site — questions answered

Direct answers to the questions buyers ask most often.

What causes clay contamination in a construction & demolition waste remote site?

Screens blind and the chamber packs during wet weather. The usual causes are clay-bearing overburden enters with the shot rock; spray water is added without a washing circuit; transfer chutes are too narrow for sticky material. scalp clay at the grizzly before primary crushing.

Which crusher train suits construction & demolition waste at 60–180 t/h?

A typical configuration is mobile impact + magnet + picking → screen. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 90 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call