Design basis for basalt asphalt aggregate supply
The design basis starts with the rock, not the machine. Basalt is rated at 150–300 MPa compressive strength with high abrasiveness, low moisture sensitivity and a loose bulk density around 1.50 t/m³. Very abrasive and tough; wear cost per tonne, not peak throughput, usually decides the circuit and the liner alloy. A change in one stage changes the circulating load in all the others.
A asphalt aggregate supply must produce cubical, low-fines chips for asphalt plants, constrained by a narrow 5–16 mm fraction with low moisture. The commercial priority is particle shape. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of railway ballast, 0–5, 5–16, 16–31.5 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Basalt · 150–300 MPa · abrasion high |
| Design throughput | 150 t/h saleable product (100–220 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | railway ballast, 0–5, 5–16, 16–31.5 mm |
| Loose bulk density | 1.50 t/m³ |
| Suggested circuit | jaw → cone → VSI → 3-deck screen |

Why off-specification grading appears in this circuit
The product sieve curve drifts outside its envelope between shifts. In a basalt asphalt aggregate supply this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- CSS has moved as liners wear and was not re-measured
- screen media is worn, blinded or stretched
- feed gradation changes as the quarry face advances
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) run a full sieve analysis on each product fraction; 2) compare current CSS with the commissioning log; 3) inspect every deck for torn or blinded panels. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For basalt at 150 t/h the working train is jaw → cone → VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for basalt and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.50 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 480 kW order-of-magnitude connected load |
The corrective actions for off-specification grading are applied on top of this base circuit: measure and log css after every liner change; set a screen-panel replacement interval based on aperture wear; adjust the closed-circuit return rate before changing the crusher setting.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 70% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Run a full sieve analysis on each product fraction
- Compare current CSS with the commissioning log
- Inspect every deck for torn or blinded panels
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast, 0–5, 5–16, 16–31.5 mm |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 480 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for basalt, while particle shape determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.