Overview
A practical Limestone crushing plant configuration by capacity, with the equipment list and screening setup that HAMAC typically specifies.

30–100 t/h
- Primary jaw (PE series).
- Secondary impact or small cone.
- 2-deck screen for 2–3 products.
- Wheel or tracked for mobility.
100–300 t/h
- Primary jaw + secondary cone.
- 3-deck screen, multiple fractions.
- Dust control and conveyors.
- Stationary or modular.
300–800 t/h
- Large jaw or gyratory primary.
- Two-stage cone train.
- Multiple screens and stockpiles.
- PLC control, full dust suppression.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Limestone |
| Mohs hardness | 3 |
| Compressive strength | ~100 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
The figures above are transcribed from published HAMAC data and from the material properties of limestone; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for limestone crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Decommissioning or relocation value at the end of a five-year horizon.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Control system language, telemetry and remote diagnostics availability.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Wear-part interchangeability across machines in the same circuit.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
Ask each supplier to price the same list. Quotations for limestone crushing only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
The commissioning record becomes the reference for every liner change in the five-year plan.