Overview
A practical Granite crushing plant configuration by capacity, with the equipment list and screening setup that HAMAC typically specifies.

30–100 t/h
- Primary jaw (PE series).
- Secondary impact or small cone.
- 2-deck screen for 2–3 products.
- Wheel or tracked for mobility.
100–300 t/h
- Primary jaw + secondary cone.
- 3-deck screen, multiple fractions.
- Dust control and conveyors.
- Stationary or modular.
300–800 t/h
- Large jaw or gyratory primary.
- Two-stage cone train.
- Multiple screens and stockpiles.
- PLC control, full dust suppression.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Granite |
| Mohs hardness | 6.5 |
| Compressive strength | ~180 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone (+ VSI for sand) |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
At mine pre-beneficiation feed, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | minimal civil works |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for granite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Control system language, telemetry and remote diagnostics availability.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Ask each supplier to price the same list. Quotations for granite crushing only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 19% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying minimal civil works on price alone and losing it in availability.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Calibrate the belt scale and any level probes against a known load.
- Record the baseline grading curve for each product fraction.
- Dry-run the plant empty for the specified period and record vibration.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Measure noise and dust at the operator position against the local limit.
The commissioning record becomes the reference for every liner change in the single-project plan.