Overview
Buying a Mobile Jaw Crusher Plant direct from HAMAC removes the trading margin and gives you engineering support from enquiry to commissioning.

Why buy direct
- One project manager for the whole order.
- Workshop assembly, test and container loading plan.
- Flow-sheet design, layout and foundation reference.
- Installation supervision, training and 24h technical response.
Export & documentation
Quoted FOB / CFR / CIF. Documentation applicable to your market (CE where required), Spanish manuals for LatAm, motors set to local voltage.
How to order
Send project data → receive design + budget in 24h → refine drawings → manufacture → install.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for mobile jaw crusher plant — a lower price often means one of these parameters was quietly reduced.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | tight grading compliance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Dust and noise control designed to the local emission limits for your market.
- Closed-side setting range and whether automatic setting regulation is included.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
For contract crushing on short-term sites, protect the tight grading compliance requirement explicitly in the contract documents.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Measure and log the as-new CSS / setting for future wear comparison.
- Test emergency stops, pull wires and interlock trips in sequence.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check lubrication levels, grease lines and oil cooler operation.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
On a remote mine site, allow extra time for the dust and noise measurements.