Overview
Buying a European Tech. Jaw Crusher direct from HAMAC removes the trading margin and gives you engineering support from enquiry to commissioning.

Why buy direct
- One project manager for the whole order.
- Workshop assembly, test and container loading plan.
- Flow-sheet design, layout and foundation reference.
- Installation supervision, training and 24h technical response.
Export & documentation
Quoted FOB / CFR / CIF. Documentation applicable to your market (CE where required), Spanish manuals for LatAm, motors set to local voltage.
How to order
Send project data → receive design + budget in 24h → refine drawings → manufacture → install.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | European Tech. Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | ten-year view |
At cement raw-meal preparation, the ranking of these parameters changes: lowest energy per tonne usually becomes the deciding constraint rather than the headline tonnage.
Published European Tech. Jaw Crusher model data
| Model | Feed opening | Motor Power | Rotation speed | Jaw plate length | Max single part weight | Total weight |
|---|---|---|---|---|---|---|
| 6CX80 | 800×510 mm | 75 kW | 350 rpm | 1100 mm | 2870 kg | 7520 kg |
| 6CX96 | 930×580 mm | 75(90) kW | 300 rpm | 1380 mm | 4500 kg | 12000 kg |
| 6CX106 | 1060×700 mm | 110 kW | 280 rpm | 1450 mm | 7800 kg | 19000 kg |
| 6CX110 | 1100×850 mm | 132(160) kW | 230 rpm | 1800 mm | 9000 kg | 25060 kg |
| 6CX125 | 1250×950 mm | 160(132) kW | 220 rpm | 2000 mm | 12960 kg | 36700 kg |
| 6CX140 | 1400×1070 mm | 200(160) kW | 220 rpm | 2100 mm | 15950 kg | 45300 kg |
| 6CX145 | 1400×1100 mm | 200 kW | 220 rpm | 2300 mm | 18600 kg | 53800 kg |
| 6CX160 | 1600×1200 mm | 250(200) kW | 220 rpm | 2500 mm | 21380 kg | 68600 kg |
The European Tech. jaw crusher, developed using advanced international crushing technology, is designed for high-efficiency crushing of hard, abrasive materials. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for european tech. jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against the feed material.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Product sampling points and the lab equipment needed for routine grading checks.
- Dust and noise control designed to the local emission limits for your market.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Wear-part interchangeability across machines in the same circuit.
- Closed-side setting range and whether automatic setting regulation is included.
- Energy draw in kW and the expected kWh per tonne at the design duty.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On cement raw-meal preparation, the lowest energy per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
For cement raw-meal preparation, protect the lowest energy per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Test emergency stops, pull wires and interlock trips in sequence.
The commissioning record becomes the reference for every liner change in the ten-year plan.