Overview
Published Compound Cone Crusher specifications below are nominal values transcribed from HAMAC data. Actual performance depends on feed gradation, moisture, setting and screening efficiency.

Specification table
| Parameter | Value |
|---|---|
| HMC1650C2-D | Coarse 34 mm |
| HMC1650C-D | Coarse 34 mm |
| HMC1650Z-D | Medium Coarse 34 mm |
| HMC1650S-X | Fine 28 mm |
| HMC1400C-D | Coarse 30 mm |
| HMC1400Z-D | Medium Coarse 30 mm |
| HMC1400Z-X | Medium Coarse 25 mm |
How to read the data
- Rated capacity is at a specified CSS / setting and material — treat it as saleable product, not crusher throughput.
- Feed size limit protects the chamber; oversize feed causes bridging.
- Motor power scales with rotor / chamber size, not linearly with capacity.
Selecting the right model
Match the model to your target t/h at the required product size, then confirm with a HAMAC engineer before order.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Compound Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | ten-year view |
At seasonal road-project supply, the ranking of these parameters changes: lowest energy per tonne usually becomes the deciding constraint rather than the headline tonnage.
Published Compound Cone Crusher model data
| Model | Cavity Type | Stroke | Feed Limit | Exit Aperture | Capacity | Motor Power | Weight |
|---|---|---|---|---|---|---|---|
| HMC1650C2-D | Coarse | 34 mm | 300 mm | 35-65 mm | 280-610 t/h | 250 kw | 35 t |
| HMC1650C-D | Coarse | 34 mm | 260 mm | 30-60 mm | 265-580 t/h | 250 kw | 35 t |
| HMC1650Z-D | Medium Coarse | 34 mm | 240 mm | 25-60 mm | 240-550 t/h | 250 kw | 35 t |
| HMC1650S-X | Fine | 28 mm | 130 mm | 20-45 mm | 180-350 t/h | 250 kw | 35 t |
| HMC1400C-D | Coarse | 30 mm | 235 mm | 30-60 mm | 210-530 t/h | 220 kw | 25 t |
| HMC1400Z-D | Medium Coarse | 30 mm | 215 mm | 25-50 mm | 200-500 t/h | 220 kw | 25 t |
| HMC1400Z-X | Medium Coarse | 25 mm | 180 mm | 22-45 mm | 180-475 t/h | 220 kw | 25 t |
| HMC1400S-X | Fine | 25 mm | 100 mm | 19-40 mm | 130-260 t/h | 220 kw | 25 t |
HMC series compound spring cone crusher is a more convenient cone crusher which is researched on the base of traditional spring cone crusher. Read the table column by column against seasonal road-project supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a coastal export terminal |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for compound cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Closed-side setting range and whether automatic setting regulation is included.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Dust and noise control designed to the local emission limits for your market.
- Control system language, telemetry and remote diagnostics availability.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Buying lowest energy per tonne on price alone and losing it in availability.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in your market until erection has already started.
Review the list with a full-time plant team before the order is placed — they will recognise most of them.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.