Overview
Practical, numbers-first guidance on the Mobile 3 In 1 Crushing & Screening Plant — written for engineers specifying, buying and running crushing plants.

Abnormal noise / vibration
- Check for loose liner bolts or foreign metal in feed.
- Verify foundation bolts and coupling alignment.
- Listen for bearing distress; schedule replacement.
Low output
- Worn liners / blow bars reduce reduction.
- Wrong CSS / setting for target product.
- Screen blinding limits throughput.
Poor product shape
- Increase reduction in the shaping stage.
- Verify VSI rotor speed / anvil.
- Re-check screen mesh.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile 3 In 1 Crushing & Screening Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | ten-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Mobile 3 In 1 Crushing & Screening Plant model data
| Model | Vibrating feeder | Impact crusher | Vibrating screen | Main belt | Capacity (t/h) |
|---|---|---|---|---|---|
| K3-PF1214-3C | GZD1142 | PFV1214 | 3YK1848 | B1000 | 100–200 |
| K3-LF150-3C | GZD9638 | LF150 | 3YK1548 | B800 | 80–150 |
| K3-LF250-3C | GZD1142 | LF250 | 3YK1848 | B1000 | 150–300 |
Feeding, crushing and screening on one wheel chassis — 80–300 t/h — for contractors who need a complete plant with minimal setup. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for mobile 3 in 1 crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Whether the quoted t/h is achieved at high-tonnage aggregate supply or under ideal laboratory feed.
- Wear-part interchangeability across machines in the same circuit.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Dust and noise control designed to the local emission limits for your market.
- Energy draw in kW and the expected kWh per tonne at the design duty.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record power draw, tonnage and chamber pressure at steady state.
- Test emergency stops, pull wires and interlock trips in sequence.
- Calibrate the belt scale and any level probes against a known load.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
On a remote mine site, allow extra time for the dust and noise measurements.