Overview
A under 50 tph crushing plant is a common size for Peru. Main machines: small jaw + impact/cone, skid or mobile. Contractor and pilot scale, fast set-up.

Main equipment
- small jaw + impact/cone, skid or mobile
- Shipped to Callao.
- Configured to 380V 60Hz / NTP.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Peru
- Port: Callao.
- Voltage: 380V 60Hz.
- Standards: NTP.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 10–50 t/h |
| Typical main line | small jaw + impact/cone, skid or mobile |
| Scale note | Contractor and pilot scale, fast set-up. |
| Destination port | Callao |
| Site supply | 380V 60Hz |
| Local standards | NTP |
| Region | South America |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
At contract crushing on short-term sites, the ranking of these parameters changes: fast mobilisation usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | fast mobilisation |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Size the primary stage for 10–50 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Wear-part interchangeability across machines in the same circuit.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Closed-side setting range and whether automatic setting regulation is included.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
For contract crushing on short-term sites, give the fast mobilisation line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 49% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Buying fast mobilisation on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 10–50 t/h.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Overlooking dust, noise and water permits in Peru until erection has already started.
For contract crushing on short-term sites, protect the fast mobilisation requirement explicitly in the contract documents.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm the direction and tension of every belt under no load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Sample each product fraction and compare with the specification.
Keep the signed record; it is the only defensible baseline for later performance disputes.