Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Jebel Ali, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for UAE.
- Erection supervision, 415V 50Hz power tie-in and training.
Market parameters for UAE
| Item | Reference |
|---|---|
| Region | Middle East |
| Port | Jebel Ali |
| Voltage / frequency | 415V 50Hz |
| Standards | ESMA |
| Typical feed | Limestone, Gabbro |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Jebel Ali |
| Site supply | 415V 50Hz |
| Local standards | ESMA |
| Region | Middle East |
| Assumed duty | continuous quarry production |
| Evaluation horizon | three-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and three-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Specify motors, starters and documentation for 415V 50Hz and ESMA before manufacture.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Book container or flat-rack space to Jebel Ali and prepare the customs document set in advance.
A realistic programme reserves time for permits, foundation curing and shipping to UAE before any steel is cut.
What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying maximum mechanical availability on price alone and losing it in availability.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure noise and dust at the operator position against the local limit.
- Record the baseline grading curve for each product fraction.
- Check belt tracking, chute build-up and transfer-point dust.
- Measure and log the as-new CSS / setting for future wear comparison.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
Keep the signed record; it is the only defensible baseline for later performance disputes.