Overview
HAMAC supplies crushing and grinding equipment to Zimbabwe, shipped to Beira and quoted to local standards (SAZS). Power is configured for 380V 50Hz.

Crushing equipment for Zimbabwe
- Popular material: Gold ore, Chrome.
- Destination port: Beira.
- Voltage / frequency: 380V 50Hz.
- Standards: SAZS.
What HAMAC provides
- Plant design for gold ore and your capacity.
- Equipment configured to 380V 50Hz and SAZS.
- FOB / CFR / CIF quotation to Beira.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Zimbabwe, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Beira |
| Site supply | 380V 50Hz |
| Local standards | SAZS |
| Region | Africa |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | five-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Book container or flat-rack space to Beira and prepare the customs document set in advance.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Wear-part interchangeability across machines in the same circuit.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Closed-side setting range and whether automatic setting regulation is included.
- Whether the quoted t/h is achieved at high-tonnage aggregate supply or under ideal laboratory feed.
- Control system language, telemetry and remote diagnostics availability.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
The commissioning record becomes the reference for every liner change in the five-year plan.