Overview
HAMAC supplies crushing and grinding equipment to Ethiopia, shipped to Djibouti and quoted to local standards (ES). Power is configured for 380V 50Hz.

Crushing equipment for Ethiopia
- Popular material: Limestone, Basalt.
- Destination port: Djibouti.
- Voltage / frequency: 380V 50Hz.
- Standards: ES.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 380V 50Hz and ES.
- FOB / CFR / CIF quotation to Djibouti.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Ethiopia, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Djibouti |
| Site supply | 380V 50Hz |
| Local standards | ES |
| Region | Africa |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and single-project operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | strict product cubicity |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Specify motors, starters and documentation for 380V 50Hz and ES before manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Book container or flat-rack space to Djibouti and prepare the customs document set in advance.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Ethiopia.

What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Wear-part interchangeability across machines in the same circuit.
- Control system language, telemetry and remote diagnostics availability.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the strict product cubicity objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Buying strict product cubicity on price alone and losing it in availability.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Record power draw, tonnage and chamber pressure at steady state.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On a greenfield site, allow extra time for the dust and noise measurements.