Overview
HAMAC supplies crushing and grinding equipment to Poland, shipped to Gdańsk and quoted to local standards (PN EN). Power is configured for 400V 50Hz.

Crushing equipment for Poland
- Popular material: Limestone, Aggregates.
- Destination port: Gdańsk.
- Voltage / frequency: 400V 50Hz.
- Standards: PN EN.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 400V 50Hz and PN EN.
- FOB / CFR / CIF quotation to Gdańsk.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Poland, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Gdańsk |
| Site supply | 400V 50Hz |
| Local standards | PN EN |
| Region | Europe |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | tight grading compliance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Whether the quoted t/h is achieved at demolition and recycling duties or under ideal laboratory feed.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Control system language, telemetry and remote diagnostics availability.
- Dust and noise control designed to the local emission limits for Poland.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Poland is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in Poland until erection has already started.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Buying tight grading compliance on price alone and losing it in availability.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Using one liner profile for both secondary and tertiary stages.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify rotation direction on every motor before coupling.
The commissioning record becomes the reference for every liner change in the ten-year plan.