Overview
HAMAC supplies crushing and grinding equipment to Canada, shipped to Vancouver and quoted to local standards (CSA). Power is configured for 575V 60Hz.

Crushing equipment for Canada
- Popular material: Granite, Aggregates.
- Destination port: Vancouver.
- Voltage / frequency: 575V 60Hz.
- Standards: CSA.
What HAMAC provides
- Plant design for granite and your capacity.
- Equipment configured to 575V 60Hz and CSA.
- FOB / CFR / CIF quotation to Vancouver.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Canada, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Vancouver |
| Site supply | 575V 60Hz |
| Local standards | CSA |
| Region | North America |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | fast mobilisation |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Book container or flat-rack space to Vancouver and prepare the customs document set in advance.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Canada.

What to verify before you sign
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Decommissioning or relocation value at the end of a single-project horizon.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Local service partner, technician travel time and visa requirements for Canada.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Nameplate data for 575V 60Hz and the CSA certificate set.
- Wear-part interchangeability across machines in the same circuit.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the single-project review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Sample each product fraction and compare with the specification.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
Keep the signed record; it is the only defensible baseline for later performance disputes.