Overview
HAMAC supplies crushing and grinding equipment to France, shipped to Le Havre and quoted to local standards (NF EN). Power is configured for 400V 50Hz.

Crushing equipment for France
- Popular material: Limestone, Granite.
- Destination port: Le Havre.
- Voltage / frequency: 400V 50Hz.
- Standards: NF EN.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 400V 50Hz and NF EN.
- FOB / CFR / CIF quotation to Le Havre.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for France, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Le Havre |
| Site supply | 400V 50Hz |
| Local standards | NF EN |
| Region | Europe |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Specify motors, starters and documentation for 400V 50Hz and NF EN before manufacture.
- Confirm the haul-road and stockpile plan with a coastal export terminal in mind before fixing conveyor lengths.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Nameplate data for 400V 50Hz and the NF EN certificate set.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Product sampling points and the lab equipment needed for routine grading checks.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the ten-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Using one liner profile for both secondary and tertiary stages.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Check lubrication levels, grease lines and oil cooler operation.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
On a coastal export terminal, allow extra time for the dust and noise measurements.