Overview
HAMAC supplies crushing and grinding equipment to Tanzania, shipped to Dar es Salaam and quoted to local standards (TBS). Power is configured for 415V 50Hz.

Crushing equipment for Tanzania
- Popular material: Gold ore, Granite.
- Destination port: Dar es Salaam.
- Voltage / frequency: 415V 50Hz.
- Standards: TBS.
What HAMAC provides
- Plant design for gold ore and your capacity.
- Equipment configured to 415V 50Hz and TBS.
- FOB / CFR / CIF quotation to Dar es Salaam.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Tanzania, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Dar es Salaam |
| Site supply | 415V 50Hz |
| Local standards | TBS |
| Region | Africa |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | five-year view |
At seasonal road-project supply, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | minimal civil works |
| Evaluation horizon | five-year view |
| Site condition | a brownfield extension |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Specify motors, starters and documentation for 415V 50Hz and TBS before manufacture.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Product sampling points and the lab equipment needed for routine grading checks.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On seasonal road-project supply, the minimal civil works objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Overlooking dust, noise and water permits in Tanzania until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Using one liner profile for both secondary and tertiary stages.
For seasonal road-project supply, protect the minimal civil works requirement explicitly in the contract documents.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the five-year plan.