Overview
A 200–300 tph plant for quartz (Mohs 7, ~150 MPa, high abrasion). Recommended circuit: jaw + cone + VSI.

Quartz at this scale
| Capacity | 200–300 t/h |
|---|---|
| Material | Quartz (High abrasion) |
| Circuit | jaw + cone + VSI |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Notes
High SiO2; premium wear parts recommended.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Quartz |
| Mohs hardness | 7 |
| Compressive strength | ~150 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | fast mobilisation |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for quartz crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Apply jaw + cone + VSI; the reduction mechanism must suit high abrasion and a compressive strength near 150 MPa.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Review the crusher chamber profile with the liner supplier against Quartz (Mohs 7, ~150 MPa, high abrasion).
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Wear-part interchangeability across machines in the same circuit.
- Liner alloy: Mn18 with ceramic inserts is a common starting point for quartz at high abrasion.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 19% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Buying fast mobilisation on price alone and losing it in availability.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 200–300 t/h.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Calibrate the belt scale and any level probes against a known load.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
- Verify rotation direction on every motor before coupling.
- Check belt tracking, chute build-up and transfer-point dust.
Keep the signed record; it is the only defensible baseline for later performance disputes.