Overview
A 200–300 tph plant for dolomite (Mohs 3.5, ~110 MPa, low abrasion). Recommended circuit: jaw + impact.

Dolomite at this scale
| Capacity | 200–300 t/h |
|---|---|
| Material | Dolomite (Low abrasion) |
| Circuit | jaw + impact |
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
Notes
Flux stone and aggregate.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Dolomite |
| Mohs hardness | 3.5 |
| Compressive strength | ~110 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | seven-year view |
At demolition and recycling duties, the ranking of these parameters changes: simple operator maintenance usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for dolomite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Survey the feed: Dolomite (Mohs 3.5, ~110 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Dust and noise control designed to the local emission limits for your market.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
For demolition and recycling duties, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 17% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming the manufacturer's warranty covers wear parts and consumables.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm all guards, emergency stops and pull-wire switches function.
- Calibrate the belt scale and any level probes against a known load.
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
The commissioning record becomes the reference for every liner change in the seven-year plan.