Overview
A 100–200 tph plant for limestone (Mohs 3, ~100 MPa, low abrasion). Recommended circuit: jaw + impact.

Limestone at this scale
| Capacity | 100–200 t/h |
|---|---|
| Material | Limestone (Low abrasion) |
| Circuit | jaw + impact |
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
- Mobile Impact Crusher Plant
Notes
Soft, low abrasion; impact crushing gives good shape.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Limestone |
| Mohs hardness | 3 |
| Compressive strength | ~100 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
At cement raw-meal preparation, the ranking of these parameters changes: lowest cost per tonne usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for limestone crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Review the crusher chamber profile with the liner supplier against Limestone (Mohs 3, ~100 MPa, low abrasion).
- Apply jaw + impact; the reduction mechanism must suit low abrasion and a compressive strength near 100 MPa.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Survey the feed: Limestone (Mohs 3, ~100 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Local service partner, technician travel time and visa requirements for your market.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Decommissioning or relocation value at the end of a three-year horizon.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 100–200 t/h.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 6% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 100–200 t/h.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
The commissioning record becomes the reference for every liner change in the three-year plan.