Overview
A 50–100 tph plant for andesite (Mohs 6, ~170 MPa, high abrasion). Recommended circuit: jaw + cone.

Andesite at this scale
| Capacity | 50–100 t/h |
|---|---|
| Material | Andesite (High abrasion) |
| Circuit | jaw + cone |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
Notes
Hard volcanic rock; good road aggregate.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Andesite |
| Mohs hardness | 6 |
| Compressive strength | ~170 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone |
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
These values are the starting point for a written proposal on andesite crushing; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a coastal export terminal |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for andesite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Apply jaw + cone; the reduction mechanism must suit high abrasion and a compressive strength near 170 MPa.
- Lay out the PE jaw + PF impact / cone + 2-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Review the crusher chamber profile with the liner supplier against Andesite (Mohs 6, ~170 MPa, high abrasion).
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Shortening this sequence is possible on a coastal export terminal, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Liner alloy: Mn22 is a common starting point for andesite at high abrasion.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 50–100 t/h.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Control system language, telemetry and remote diagnostics availability.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 49% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 20% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
Keep the signed record; it is the only defensible baseline for later performance disputes.