Overview
This page brings together the published VSI Vertical Shaft Impact Crusher (Sand Making Machine) model data and the practical details of importing it into Turkey — power supply, standards, shipping and commissioning. Popular feed materials in the market include Basalt, Limestone.

Published VSI Vertical Shaft Impact Crusher (Sand Making Machine) data
| Published parameter | Nominal value |
|---|---|
| VSI7611 | ≤35 60–90 |
| VSI7615 | ≤35 70–140 |
| VSI8518 | ≤40 100–130 |
| VSI8522 | ≤40 120–160 |
| VSI9526 | ≤45 150–190 |
| VSI9532 | ≤45 180–220 |
Local conditions in Turkey
- Destination port: Istanbul.
- Site supply: 380V 50Hz.
- Standards: TS EN.
- Common materials: Basalt, Limestone.
- Region: Europe/Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Istanbul, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to TS EN. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Istanbul |
| Site supply | 380V 50Hz |
| Local standards | TS EN |
| Region | Europe/Asia |
| Machine line | VSI Vertical Shaft Impact Crusher (Sand Making Machine) |
| Category | Sand Making & Washing |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for vsi vertical shaft impact crusher (sand making machine) cannot be compared on scope.
Published VSI Vertical Shaft Impact Crusher (Sand Making Machine) model data
| Model | Max. feeding size (mm) | Nominal through capacity (t/h) | Motor power (kW) |
|---|---|---|---|
| VSI7611 | ≤35 | 60–90 | 55×2 |
| VSI7615 | ≤35 | 70–140 | 75×2 |
| VSI8518 | ≤40 | 100–130 | 90×2 |
| VSI8522 | ≤40 | 120–160 | 110×2 |
| VSI9526 | ≤45 | 150–190 | 132×2 |
| VSI9532 | ≤45 | 180–220 | 160×2 |
| VSI1140 | ≤50 | 225–260 | 200×2 |
| VSI1145 | ≤50 | 250–300 | 220×2 |
VSI sand making machine, 60–500 t/h, for manufactured sand and aggregate shaping with rock-on-rock crushing and interchangeable wear parts. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | a coastal export terminal |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for vsi vertical shaft impact crusher (sand making machine) may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Dust and noise control designed to the local emission limits for Turkey.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Local service partner, technician travel time and visa requirements for Turkey.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Overlooking dust, noise and water permits in Turkey until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
For high-tonnage aggregate supply, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure noise and dust at the operator position against the local limit.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
Keep the signed record; it is the only defensible baseline for later performance disputes.