Overview
This page brings together the published PE Series Jaw Crusher model data and the practical details of importing it into Sri Lanka — power supply, standards, shipping and commissioning. Popular feed materials in the market include Granite, Limestone.

Published PE Series Jaw Crusher data
| Published parameter | Nominal value |
|---|---|
| PEX250x750 | 250x750 mm 210 mm |
| PEX250x1000 | 250x1000 mm 210 mm |
| PEX250x1200 | 250x1200 mm 210 mm |
| PEX300x1300 | 300x1300 mm 250 mm |
| PE400×600 | 400×600 mm 340 mm |
| PE500×750 | 500×750 mm 425 mm |
Local conditions in Sri Lanka
- Destination port: Colombo.
- Site supply: 400V 50Hz.
- Standards: SLS.
- Common materials: Granite, Limestone.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Colombo, sets motors and starters to 400V 50Hz, and supplies the certificate set applicable to SLS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Colombo |
| Site supply | 400V 50Hz |
| Local standards | SLS |
| Region | Asia |
| Machine line | PE Series Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | continuous quarry production |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for Sri Lanka should update the same fields so the equipment list stays traceable.
Published PE Series Jaw Crusher model data
| Model | Input Size | Max Feeding Size | Output Range | Capacity | Engine Power | Weight |
|---|---|---|---|---|---|---|
| PEX250x750 | 250x750 mm | 210 mm | 25-60 mm | 13-35 T/H | 30 KW | 5.5 T |
| PEX250x1000 | 250x1000 mm | 210 mm | 25-60 mm | 16-52 T/H | 37 KW | 7 T |
| PEX250x1200 | 250x1200 mm | 210 mm | 25-60 mm | 20-61 T/H | 55 KW | 9.5 T |
| PEX300x1300 | 300x1300 mm | 250 mm | 20-90 mm | 16-105 T/H | 75 KW | 15.6 T |
| PE400×600 | 400×600 mm | 340 mm | 40-100 mm | 16-60 T/H | 30 KW | 6.7 T |
| PE500×750 | 500×750 mm | 425 mm | 50-100 mm | 40-110 T/H | 55 KW | 11.7 T |
| PE600×900 | 600×900 mm | 500 mm | 65-180 mm | 80-180 T/H | 55-75 KW | 16.1 T |
| PE750×1060 | 750×1060 mm | 630 mm | 80-180 mm | 110-320 T/H | 90-110 KW | 30.1 T |
Jaw crushers are often used for primary crushing in mine material crushing. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for pe series jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Specify motors, starters and documentation for 400V 50Hz and SLS before manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
A realistic programme reserves time for permits, foundation curing and shipping to Sri Lanka before any steel is cut.

What to verify before you sign
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Control system language, telemetry and remote diagnostics availability.
- Nameplate data for 400V 50Hz and the SLS certificate set.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Local service partner, technician travel time and visa requirements for Sri Lanka.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Ask each supplier to price the same list. Quotations for pe series jaw crusher only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Overlooking dust, noise and water permits in Sri Lanka until erection has already started.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm all guards, emergency stops and pull-wire switches function.
- Record power draw, tonnage and chamber pressure at steady state.
- Check lubrication levels, grease lines and oil cooler operation.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On a greenfield site, allow extra time for the dust and noise measurements.