Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Myanmar — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Aggregates.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Myanmar
- Destination port: Yangon.
- Site supply: 380V 50Hz.
- Standards: MSS.
- Common materials: Limestone, Aggregates.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Yangon, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to MSS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Yangon |
| Site supply | 380V 50Hz |
| Local standards | MSS |
| Region | Asia |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on mobile jaw crusher plant; they are nominal and should be confirmed against a sample test before manufacture.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Dust and noise control designed to the local emission limits for Myanmar.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Local service partner, technician travel time and visa requirements for Myanmar.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Control system language, telemetry and remote diagnostics availability.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
For high-tonnage aggregate supply, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying simple operator maintenance on price alone and losing it in availability.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Using one liner profile for both secondary and tertiary stages.
- Overlooking dust, noise and water permits in Myanmar until erection has already started.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record the baseline grading curve for each product fraction.
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.