Overview
This page brings together the published HPT Multi-Cylinder Hydraulic Cone Crusher model data and the practical details of importing it into Morocco — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Phosphates.

Published HPT Multi-Cylinder Hydraulic Cone Crusher data
| Published parameter | Nominal value |
|---|---|
| HPT100 | 90 45–140 |
| HPT200 | 160 90–250 |
| HPT300 | 220 110–440 |
| HPT400 / HPT500 | On request On request |
Local conditions in Morocco
- Destination port: Casablanca.
- Site supply: 380V 50Hz.
- Standards: NM.
- Common materials: Limestone, Phosphates.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Casablanca, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to NM. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Casablanca |
| Site supply | 380V 50Hz |
| Local standards | NM |
| Region | Africa |
| Machine line | HPT Multi-Cylinder Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | seven-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published HPT Multi-Cylinder Hydraulic Cone Crusher model data
| Model | Installed power (kW) | Capacity range (t/h) | Dimensions (mm) |
|---|---|---|---|
| HPT100 | 90 | 45–140 | 1705 × 1510 × 1583 |
| HPT200 | 160 | 90–250 | 2135 × 1750 × 1927 |
| HPT300 | 220 | 110–440 | 2725 × 2110 × 2871 |
| HPT400 / HPT500 | On request | On request | On request |
Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone through basalt, with 5–15% higher efficiency and 35–60% higher output than spring cone crushers. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | strict product cubicity |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for hpt multi-cylinder hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Specify motors, starters and documentation for 380V 50Hz and NM before manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Book container or flat-rack space to Casablanca and prepare the customs document set in advance.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Nameplate data for 380V 50Hz and the NM certificate set.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Whether the quoted t/h is achieved at demolition and recycling duties or under ideal laboratory feed.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Dust and noise control designed to the local emission limits for Morocco.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the seven-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
On a remote mine site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
The commissioning record becomes the reference for every liner change in the seven-year plan.