Overview
This page brings together the published MTW European Type Grinding Mill model data and the practical details of importing it into Kenya — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Basalt.

Published MTW European Type Grinding Mill data
| Published parameter | Nominal value |
|---|---|
| Quantity of roller (PCS) | 4 4 |
| Inner diameter of ring (mm) | 1100 1380 |
| Rotary speed of main frame (r/min) | 120 96 |
| Max. Feeding size (mm) | < 30 < 35 |
| Output size (mm) | 1.6~0.045 1.6~0.045 |
| Output fineness | 0.038 0.038 |
Local conditions in Kenya
- Destination port: Mombasa.
- Site supply: 415V 50Hz.
- Standards: KS.
- Common materials: Limestone, Basalt.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Mombasa, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to KS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Machine line | MTW European Type Grinding Mill |
| Category | Grinding Mills |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on mtw european type grinding mill; they are nominal and should be confirmed against a sample test before manufacture.
Published MTW European Type Grinding Mill model data
| Item | MTW110 | MTW138 | MTW175 | MTW215 |
|---|---|---|---|---|
| Quantity of roller (PCS) | 4 | 4 | 5 | 5 |
| Inner diameter of ring (mm) | 1100 | 1380 | 1750 | 2150 |
| Rotary speed of main frame (r/min) | 120 | 96 | 75 | 65 |
| Max. Feeding size (mm) | < 30 | < 35 | < 40 | < 50 |
| Output size (mm) | 1.6~0.045 | 1.6~0.045 | 1.6~0.045 | 1.6-0.055 |
| Output fineness | 0.038 | 0.038 | 0.038 | 0.045 |
| Capacity (t/h) | 3.5~10 | 6.5~15 | 11~25 | 20-50 |
| Total weight (t) | 18 | 28.5 | 46 | 96 |
MTW European Tech. grinding mill (Raymond mill) is a national patented product developed by our company on the basis of absorbing European grinding technology and concepts. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | simple operator maintenance |
| Evaluation horizon | ten-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for mtw european type grinding mill may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Book container or flat-rack space to Mombasa and prepare the customs document set in advance.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Dust and noise control designed to the local emission limits for Kenya.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Wear-part interchangeability across machines in the same circuit.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Closed-side setting range and whether automatic setting regulation is included.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Product sampling points and the lab equipment needed for routine grading checks.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in Kenya until erection has already started.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure noise and dust at the operator position against the local limit.
- Record the baseline grading curve for each product fraction.
Keep the signed record; it is the only defensible baseline for later performance disputes.