Overview
This page brings together the published PF Impact Crusher model data and the practical details of importing it into Japan — power supply, standards, shipping and commissioning. Popular feed materials in the market include Granite, Limestone.

Published PF Impact Crusher data
| Published parameter | Nominal value |
|---|---|
| PF-1007 | Φ1000×700 mm 400×730 mm |
| PF-1010 | Φ1000×1050 mm 400×1080 mm |
| PF-1210 | Φ1250×1050 mm 400×1080 mm |
| PF-1214 | Φ1250×1400 mm 400×1430 mm |
| PF-1315 | Φ1320×1500 mm 860×1520 mm |
| PF-1520 | Φ1500×2000 mm 830×2040 mm |
Local conditions in Japan
- Destination port: Yokohama.
- Site supply: 200V 50/60Hz.
- Standards: JIS.
- Common materials: Granite, Limestone.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Yokohama, sets motors and starters to 200V 50/60Hz, and supplies the certificate set applicable to JIS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Yokohama |
| Site supply | 200V 50/60Hz |
| Local standards | JIS |
| Region | Asia |
| Machine line | PF Impact Crusher |
| Category | Impact Crusher |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on pf impact crusher; they are nominal and should be confirmed against a sample test before manufacture.
Published PF Impact Crusher model data
| Model | Rotor size | Feed opening | Max. Feeding size | Capacity | Motor Power | Weight | Overall dimension |
|---|---|---|---|---|---|---|---|
| PF-1007 | Φ1000×700 mm | 400×730 mm | 300 mm | 30-70 t/h | 37-45 kW | 12 t | 2330×1660×2300 mm |
| PF-1010 | Φ1000×1050 mm | 400×1080 mm | 350 mm | 50-90 t/h | 45-55 kW | 15 t | 2370×1700×2390 mm |
| PF-1210 | Φ1250×1050 mm | 400×1080 mm | 350 mm | 70-130 t/h | 110 kW | 17.7 t | 2680×2160×2800 mm |
| PF-1214 | Φ1250×1400 mm | 400×1430 mm | 350 mm | 100-180 t/h | 132 kW | 22.4 t | 2650×2460×2800 mm |
| PF-1315 | Φ1320×1500 mm | 860×1520 mm | 500 mm | 130-250 t/h | 220 kW | 27 t | 3180×2720×2620 mm |
| PF-1520 | Φ1500×2000 mm | 830×2040 mm | 700 mm | 300-550 t/h | 315-400 kW | 50.6 t | 3959×3564×3330 mm |
| PF-1620 | Φ1600×2000 mm | 2000×1600 mm | 500 mm | 400-700 t/h | 400-500 kW | 58 t | 4259×3660×3450 mm |
| PF-1820 | Φ1800×2000 mm | 1260×2040 mm | 800 mm | 600-800 t/h | 630-710 kW | 83.21 t | 4400×3866×4009 mm |
The impact crusher (impact crusher) is a new generation of impact crusher developed in combination with the specific working conditions of the sand and gravel. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for pf impact crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Specify motors, starters and documentation for 200V 50/60Hz and JIS before manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Wear-part interchangeability across machines in the same circuit.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Decommissioning or relocation value at the end of a five-year horizon.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Ask each supplier to price the same list. Quotations for pf impact crusher only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Using one liner profile for both secondary and tertiary stages.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
For mine pre-beneficiation feed, protect the fast mobilisation requirement explicitly in the contract documents.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Record the baseline grading curve for each product fraction.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm the direction and tension of every belt under no load.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
- Sample each product fraction and compare with the specification.
The commissioning record becomes the reference for every liner change in the five-year plan.