Overview
Crushing prepares feed for grinding and beneficiation at high availability. In Nigeria the most frequently processed feed materials are Granite, Limestone, and equipment is normally delivered through Lagos on 415V 50Hz supplies.

Materials in scope
- Iron ore — Mohs 5.5, ~160 MPa, medium abrasion
- Copper ore — Mohs 4, ~120 MPa, medium abrasion
- Gold ore — Mohs 4, ~110 MPa, medium abrasion
- Manganese ore — Mohs 4, ~130 MPa, medium abrasion
Recommended machines
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- Symons Cone Crusher
Engineering for Nigeria
| Item | Reference |
|---|---|
| Port | Lagos |
| Power | 415V 50Hz |
| Standards | SON |
| Region | Africa |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Lagos |
| Site supply | 415V 50Hz |
| Local standards | SON |
| Region | Africa |
| Application | Metal Ore & Mining |
| Typical feed | Iron ore, Copper ore, Gold ore, Manganese ore |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
At manufactured-sand production, the ranking of these parameters changes: simple operator maintenance usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | five-year view |
| Site condition | an existing quarry bench |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Nameplate data for 415V 50Hz and the SON certificate set.
- Local service partner, technician travel time and visa requirements for Nigeria.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check lubrication levels, grease lines and oil cooler operation.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record the baseline grading curve for each product fraction.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
On an existing quarry bench, allow extra time for the dust and noise measurements.