Overview
A 50–100 tph crushing plant is a common size for United States. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Los Angeles / Houston.
- Configured to 460V 60Hz / ASTM / OSHA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For United States
- Port: Los Angeles / Houston.
- Voltage: 460V 60Hz.
- Standards: ASTM / OSHA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Los Angeles / Houston |
| Site supply | 460V 60Hz |
| Local standards | ASTM / OSHA |
| Region | North America |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | minimal civil works |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Specify motors, starters and documentation for 460V 60Hz and ASTM / OSHA before manufacture.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Book container or flat-rack space to Los Angeles / Houston and prepare the customs document set in advance.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Dust and noise control designed to the local emission limits for United States.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Product sampling points and the lab equipment needed for routine grading checks.
- Nameplate data for 460V 60Hz and the ASTM / OSHA certificate set.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Closed-side setting range and whether automatic setting regulation is included.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
- Confirm the direction and tension of every belt under no load.
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
The commissioning record becomes the reference for every liner change in the ten-year plan.