Overview
A 300–500 tph crushing plant is a common size for Ghana. Main machines: primary gyratory/jaw + cone train. Commercial aggregate production.

Main equipment
- primary gyratory/jaw + cone train
- Shipped to Tema.
- Configured to 415V 50Hz / GS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Ghana
- Port: Tema.
- Voltage: 415V 50Hz.
- Standards: GS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Destination port | Tema |
| Site supply | 415V 50Hz |
| Local standards | GS |
| Region | Africa |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | minimal civil works |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to Ghana is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying minimal civil works on price alone and losing it in availability.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm the direction and tension of every belt under no load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Test emergency stops, pull wires and interlock trips in sequence.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
The commissioning record becomes the reference for every liner change in the three-year plan.