Design basis for talc greenfield plant
The design basis starts with the rock, not the machine. Talc is rated at 10–30 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.30 t/m³. Very soft and plate-like; over-grinding and heat build-up are the main risks in the mill. Indicative values are starting points for a design, not guarantees.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of fine powder for plastics and coatings.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Talc · 10–30 MPa · abrasion very low |
| Design throughput | 250 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | fine powder for plastics and coatings |
| Loose bulk density | 1.30 t/m³ |
| Suggested circuit | impact → grinding mill → air classifier |

Why noise and vibration appears in this circuit
Noise limits at the site boundary are exceeded. In a talc greenfield plant this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- the crusher and screen are mounted without adequate isolation
- the plant is arranged with its loudest face toward the boundary
- worn bearings and loose liners add impact noise
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) measure boundary noise at the worst-case operating state; 2) log vibration on screen bearings; 3) inspect isolation mounts during planned stops. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For talc at 250 t/h the working train is impact → grinding mill → air classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for talc and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~313 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | grinding mill |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.30 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 740 kW order-of-magnitude connected load |
The corrective actions for noise and vibration are applied on top of this base circuit: isolate screen and crusher mounts and maintain them; orient the plant and use stockpiles as acoustic barriers; replace worn bearings and re-torque liner fasteners.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 70% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Measure boundary noise at the worst-case operating state
- Log vibration on screen bearings
- Inspect isolation mounts during planned stops
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 250 t/h nominal |
| Grading | Full sieve analysis, agreed standard, fine powder for plastics and coatings |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 740 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for talc, while a verifiable mass balance determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.