● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Environment

Quartzite quarry expansion: Noise and vibration — solution & design basis

Noise limits at the site boundary are exceeded — a 160 t/h design basis, configuration and acceptance checks.

Quartzite quarry expansion with noise and vibration is normally resolved by checking the circuit against the saleable product specification first: isolate screen and crusher mounts and maintain them. For a 160 t/h design point on quartzite, HAMAC would review jaw → cone → cone → screen, then confirm the settings with a written acceptance test. Two plants with the same nominal t/h can have very different operating costs.

160 t/hindicative design point
150–300 MPacompressive strength
150–300 t/hscenario capacity band
350 kWorder-of-magnitude installed power
Key takeaways
  1. Quartzite is very high in abrasiveness and low in moisture sensitivity; Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows.
  2. For quarry expansion the priority is throughput continuity, constrained by a shared feed point and limited stockpile area.
  3. Noise and vibration typically appears as: noise limits at the site boundary are exceeded.
  4. First corrective action: isolate screen and crusher mounts and maintain them.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for quartzite quarry expansion

The design basis starts with the rock, not the machine. Quartzite is rated at 150–300 MPa compressive strength with very high abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. Measurements are only comparable when the sieve standard is the same.

A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 160 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of high-specification aggregate and industrial sand.

Quartzite — design basis (nominal values)
ParameterIndicative value / method
Raw materialQuartzite · 150–300 MPa · abrasion very high
Design throughput160 t/h saleable product (150–300 t/h scenario band)
Maximum feed size~550 mm
Target producthigh-specification aggregate and industrial sand
Loose bulk density1.52 t/m³
Suggested circuitjaw → cone → cone → screen
Quartzite quarry expansion — Design basis for quartzite quarry expansion — HAMAC crushing and screening equipment
Quartzite quarry expansion — Design basis for quartzite quarry expansion — HAMAC crushing and screening equipment reference.

Why noise and vibration appears in this circuit

Noise limits at the site boundary are exceeded. In a quartzite quarry expansion this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.

  • the crusher and screen are mounted without adequate isolation
  • the plant is arranged with its loudest face toward the boundary
  • worn bearings and loose liners add impact noise

Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) measure boundary noise at the worst-case operating state; 2) log vibration on screen bearings; 3) inspect isolation mounts during planned stops. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For quartzite at 160 t/h the working train is jaw → cone → cone → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for quartzite and for a softer rock. Measurements are only comparable when the sieve standard is the same.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~200 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~18 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.52 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load

The corrective actions for noise and vibration are applied on top of this base circuit: isolate screen and crusher mounts and maintain them; orient the plant and use stockpiles as acoustic barriers; replace worn bearings and re-torque liner fasteners.

Quartzite quarry expansion — Recommended equipment configuration — HAMAC crushing and screening equipment
Quartzite quarry expansion — Recommended equipment configuration — HAMAC crushing and screening equipment reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 30% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.

  • Measure boundary noise at the worst-case operating state
  • Log vibration on screen bearings
  • Inspect isolation mounts during planned stops
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 160 t/h nominal
GradingFull sieve analysis, agreed standard, high-specification aggregate and industrial sand
Crusher settingCSS measured and logged, ~18 mm starting point
PowerMain-drive current at steady feed, 350 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for quartzite, while throughput continuity determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 160 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Quartzite quarry expansion — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment
Quartzite quarry expansion — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment reference.
FAQ

Quartzite quarry expansion — questions answered

Direct answers to the questions buyers ask most often.

What causes noise and vibration in a quartzite quarry expansion?

Noise limits at the site boundary are exceeded. The usual causes are the crusher and screen are mounted without adequate isolation; the plant is arranged with its loudest face toward the boundary; worn bearings and loose liners add impact noise. isolate screen and crusher mounts and maintain them.

Which crusher train suits quartzite at 150–300 t/h?

A typical configuration is jaw → cone → cone → screen. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 160 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call