Design basis for quartzite underground mine
The design basis starts with the rock, not the machine. Quartzite is rated at 150–300 MPa compressive strength with very high abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. Record the setting before adjusting it, or the baseline is lost.
A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of high-specification aggregate and industrial sand.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Quartzite · 150–300 MPa · abrasion very high |
| Design throughput | 150 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | high-specification aggregate and industrial sand |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → screen |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a quartzite underground mine this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For quartzite at 150 t/h the working train is jaw → cone → cone → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for quartzite and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 370 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, high-specification aggregate and industrial sand |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 370 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for quartzite, while compact footprint determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.