Design basis for talc greenfield plant
The design basis starts with the rock, not the machine. Talc is rated at 10–30 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.30 t/m³. Very soft and plate-like; over-grinding and heat build-up are the main risks in the mill. The reference conditions should be attached to every figure quoted.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of fine powder for plastics and coatings.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Talc · 10–30 MPa · abrasion very low |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | fine powder for plastics and coatings |
| Loose bulk density | 1.30 t/m³ |
| Suggested circuit | impact → grinding mill → air classifier |

Why off-specification grading appears in this circuit
The product sieve curve drifts outside its envelope between shifts. In a talc greenfield plant this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- CSS has moved as liners wear and was not re-measured
- screen media is worn, blinded or stretched
- feed gradation changes as the quarry face advances
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) run a full sieve analysis on each product fraction; 2) compare current CSS with the commissioning log; 3) inspect every deck for torn or blinded panels. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For talc at 220 t/h the working train is impact → grinding mill → air classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for talc and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | grinding mill |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.30 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 700 kW order-of-magnitude connected load |
The corrective actions for off-specification grading are applied on top of this base circuit: measure and log css after every liner change; set a screen-panel replacement interval based on aperture wear; adjust the closed-circuit return rate before changing the crusher setting.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 40% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Run a full sieve analysis on each product fraction
- Compare current CSS with the commissioning log
- Inspect every deck for torn or blinded panels
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, fine powder for plastics and coatings |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 700 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for talc, while a verifiable mass balance determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.