Overview
HAMAC supplies crushing and grinding equipment to Peru, shipped to Callao and quoted to local standards (NTP). Power is configured for 380V 60Hz.

Crushing equipment for Peru
- Popular material: Copper ore, Gold ore.
- Destination port: Callao.
- Voltage / frequency: 380V 60Hz.
- Standards: NTP.
What HAMAC provides
- Plant design for copper ore and your capacity.
- Equipment configured to 380V 60Hz and NTP.
- FOB / CFR / CIF quotation to Callao.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Peru, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Callao |
| Site supply | 380V 60Hz |
| Local standards | NTP |
| Region | South America |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | a brownfield extension |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Specify motors, starters and documentation for 380V 60Hz and NTP before manufacture.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
A realistic programme reserves time for permits, foundation curing and shipping to Peru before any steel is cut.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Nameplate data for 380V 60Hz and the NTP certificate set.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Local service partner, technician travel time and visa requirements for Peru.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Dust and noise control designed to the local emission limits for Peru.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Buying lowest cost per tonne on price alone and losing it in availability.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Overlooking dust, noise and water permits in Peru until erection has already started.
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
For demolition and recycling duties, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check belt tracking, chute build-up and transfer-point dust.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
The commissioning record becomes the reference for every liner change in the three-year plan.