Overview
HAMAC supplies crushing and grinding equipment to Mongolia, shipped to Tianjin and quoted to local standards (MNS). Power is configured for 380V 50Hz.

Crushing equipment for Mongolia
- Popular material: Coal, Copper ore.
- Destination port: Tianjin.
- Voltage / frequency: 380V 50Hz.
- Standards: MNS.
What HAMAC provides
- Plant design for coal and your capacity.
- Equipment configured to 380V 50Hz and MNS.
- FOB / CFR / CIF quotation to Tianjin.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Mongolia, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Tianjin |
| Site supply | 380V 50Hz |
| Local standards | MNS |
| Region | Asia |
| Assumed duty | continuous quarry production |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Specify motors, starters and documentation for 380V 50Hz and MNS before manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for Mongolia.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Closed-side setting range and whether automatic setting regulation is included.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
For continuous quarry production, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On continuous quarry production, the simple operator maintenance objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
- Buying simple operator maintenance on price alone and losing it in availability.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
For continuous quarry production, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check belt tracking, chute build-up and transfer-point dust.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Verify rotation direction on every motor before coupling.
- Check lubrication levels, grease lines and oil cooler operation.
- Dry-run the plant empty for the specified period and record vibration.
For a rotating shift crew, run through this list twice — once with the supervisor and once without.