Overview
HAMAC supplies crushing and grinding equipment to Germany, shipped to Hamburg and quoted to local standards (DIN EN). Power is configured for 400V 50Hz.

Crushing equipment for Germany
- Popular material: Limestone, Recycling.
- Destination port: Hamburg.
- Voltage / frequency: 400V 50Hz.
- Standards: DIN EN.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 400V 50Hz and DIN EN.
- FOB / CFR / CIF quotation to Hamburg.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Germany, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Hamburg |
| Site supply | 400V 50Hz |
| Local standards | DIN EN |
| Region | Europe |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | three-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | tight grading compliance |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against the feed material.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Germany.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Control system language, telemetry and remote diagnostics availability.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Closed-side setting range and whether automatic setting regulation is included.
- Nameplate data for 400V 50Hz and the DIN EN certificate set.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Overlooking dust, noise and water permits in Germany until erection has already started.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
- Measure noise and dust at the operator position against the local limit.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.