Overview
HAMAC supplies crushing and grinding equipment to Qatar, shipped to Hamad and quoted to local standards (QCS). Power is configured for 415V 50Hz.

Crushing equipment for Qatar
- Popular material: Limestone, Aggregates.
- Destination port: Hamad.
- Voltage / frequency: 415V 50Hz.
- Standards: QCS.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 415V 50Hz and QCS.
- FOB / CFR / CIF quotation to Hamad.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Qatar, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Hamad |
| Site supply | 415V 50Hz |
| Local standards | QCS |
| Region | Middle East |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Specify motors, starters and documentation for 415V 50Hz and QCS before manufacture.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
A realistic programme reserves time for permits, foundation curing and shipping to Qatar before any steel is cut.

What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Nameplate data for 415V 50Hz and the QCS certificate set.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Dust and noise control designed to the local emission limits for Qatar.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Product sampling points and the lab equipment needed for routine grading checks.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On cement raw-meal preparation, the fast mobilisation objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in Qatar until erection has already started.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
For cement raw-meal preparation, protect the fast mobilisation requirement explicitly in the contract documents.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Record the baseline grading curve for each product fraction.
For an owner-operator team, run through this list twice — once with the supervisor and once without.