Overview
HAMAC supplies crushing and grinding equipment to Bolivia, shipped to Arica and quoted to local standards (NB). Power is configured for 380V 50Hz.

Crushing equipment for Bolivia
- Popular material: Gold ore, Tin.
- Destination port: Arica.
- Voltage / frequency: 380V 50Hz.
- Standards: NB.
What HAMAC provides
- Plant design for gold ore and your capacity.
- Equipment configured to 380V 50Hz and NB.
- FOB / CFR / CIF quotation to Arica.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Bolivia, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Arica |
| Site supply | 380V 50Hz |
| Local standards | NB |
| Region | South America |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Book container or flat-rack space to Arica and prepare the customs document set in advance.
A realistic programme reserves time for permits, foundation curing and shipping to Bolivia before any steel is cut.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Nameplate data for 380V 50Hz and the NB certificate set.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Whether the quoted t/h is achieved at demolition and recycling duties or under ideal laboratory feed.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Dust and noise control designed to the local emission limits for Bolivia.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A five-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Calibrate the belt scale and any level probes against a known load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Dry-run the plant empty for the specified period and record vibration.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the five-year plan.