Overview
HAMAC supplies crushing and grinding equipment to South Korea, shipped to Busan and quoted to local standards (KS). Power is configured for 380V 60Hz.

Crushing equipment for South Korea
- Popular material: Limestone, Granite.
- Destination port: Busan.
- Voltage / frequency: 380V 60Hz.
- Standards: KS.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 380V 60Hz and KS.
- FOB / CFR / CIF quotation to Busan.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for South Korea, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Busan |
| Site supply | 380V 60Hz |
| Local standards | KS |
| Region | Asia |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for South Korea should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Specify motors, starters and documentation for 380V 60Hz and KS before manufacture.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Control system language, telemetry and remote diagnostics availability.
- Closed-side setting range and whether automatic setting regulation is included.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to South Korea is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Using one liner profile for both secondary and tertiary stages.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Verify rotation direction on every motor before coupling.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm all guards, emergency stops and pull-wire switches function.
The commissioning record becomes the reference for every liner change in the single-project plan.