Overview
A 200–300 tph plant for andesite (Mohs 6, ~170 MPa, high abrasion). Recommended circuit: jaw + cone.

Andesite at this scale
| Capacity | 200–300 t/h |
|---|---|
| Material | Andesite (High abrasion) |
| Circuit | jaw + cone |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
Notes
Hard volcanic rock; good road aggregate.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Andesite |
| Mohs hardness | 6 |
| Compressive strength | ~170 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone |
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and seven-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | tight grading compliance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for andesite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
On manufactured-sand production, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Local service partner, technician travel time and visa requirements for your market.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Control system language, telemetry and remote diagnostics availability.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Ask each supplier to price the same list. Quotations for andesite crushing only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 19% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On manufactured-sand production, the tight grading compliance objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Using one liner profile for both secondary and tertiary stages.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying tight grading compliance on price alone and losing it in availability.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check belt tracking, chute build-up and transfer-point dust.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
On a confined urban yard, allow extra time for the dust and noise measurements.