Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Vietnam — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Granite.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Vietnam
- Destination port: Ho Chi Minh.
- Site supply: 380V 50Hz.
- Standards: TCVN.
- Common materials: Limestone, Granite.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Ho Chi Minh, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to TCVN. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Ho Chi Minh |
| Site supply | 380V 50Hz |
| Local standards | TCVN |
| Region | Asia |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
Treat this as a living sheet. Every revision of the flow sheet for Vietnam should update the same fields so the equipment list stays traceable.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Specify motors, starters and documentation for 380V 50Hz and TCVN before manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for Vietnam.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Control system language, telemetry and remote diagnostics availability.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Wear-part interchangeability across machines in the same circuit.
- Nameplate data for 380V 50Hz and the TCVN certificate set.
Share this list with a rotating shift crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Vietnam is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
- Buying simple operator maintenance on price alone and losing it in availability.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
For cement raw-meal preparation, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Record the baseline grading curve for each product fraction.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Dry-run the plant empty for the specified period and record vibration.
- Check belt tracking, chute build-up and transfer-point dust.
On a brownfield extension, allow extra time for the dust and noise measurements.