Overview
Limestone (Mohs 3, ~100 MPa) is processed in Qatar for aggregates, ore or industrial minerals. HAMAC configures the circuit to local conditions: Hamad, 415V 50Hz, QCS.

Limestone properties
| Property | Value |
|---|---|
| Mohs | 3 |
| Compressive strength | 100 MPa |
| Abrasion | Low |
| Circuit | jaw + impact |
In Qatar
- Port: Hamad.
- Power: 415V 50Hz.
- Standards: QCS.
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
- Mobile Impact Crusher Plant
Budget
Send material, capacity and product sizes for a configured FOB/CIF budget to Hamad.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Limestone |
| Mohs hardness | 3 |
| Compressive strength | ~100 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Destination port | Hamad |
| Site supply | 415V 50Hz |
| Local standards | QCS |
| Region | Middle East |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | single-project view |
These values are the starting point for a written proposal on limestone crushing; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | strict product cubicity |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for limestone crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Apply jaw + impact; the reduction mechanism must suit low abrasion and a compressive strength near 100 MPa.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
A realistic programme reserves time for permits, foundation curing and shipping to Qatar before any steel is cut.

What to verify before you sign
- Dust and noise control designed to the local emission limits for Qatar.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Local service partner, technician travel time and visa requirements for Qatar.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Wear-part interchangeability across machines in the same circuit.
- Liner alloy: Mn18 with ceramic inserts is a common starting point for limestone at low abrasion.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Overlooking dust, noise and water permits in Qatar until erection has already started.
- Buying strict product cubicity on price alone and losing it in availability.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Verify rotation direction on every motor before coupling.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Record the baseline grading curve for each product fraction.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On a brownfield extension, allow extra time for the dust and noise measurements.