Design basis for gabbro concrete aggregate supply
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. The reference conditions should be attached to every figure quoted.
A concrete aggregate supply must hold a tight grading envelope for ready-mix customers, constrained by strict limits on flakiness and fines content. The commercial priority is product consistency. For this combination HAMAC works from an indicative design point of 140 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 140 t/h saleable product (120–250 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a gabbro concrete aggregate supply this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For gabbro at 140 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~175 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 410 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 40% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 140 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 410 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while product consistency determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 140 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
