Design basis for manganese ore high-altitude site
The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. A change in one stage changes the circulating load in all the others.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of sized lump and fines for smelting.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Manganese ore · 60–180 MPa · abrasion medium |
| Design throughput | 120 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | sized lump and fines for smelting |
| Loose bulk density | 1.85 t/m³ |
| Suggested circuit | jaw → impact → screen → washing |

Why clay contamination appears in this circuit
Screens blind and the chamber packs during wet weather. In a manganese ore high-altitude site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- clay-bearing overburden enters with the shot rock
- spray water is added without a washing circuit
- transfer chutes are too narrow for sticky material
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) measure surface moisture at the shift level; 2) inspect deck open area after each wet shift; 3) log the pressure drop across dust collection. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For manganese ore at 120 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load |
The corrective actions for clay contamination are applied on top of this base circuit: scalp clay at the grizzly before primary crushing; choose rubber or polyurethane media with ball trays; add a washing stage with water recovery where the specification allows.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 40% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Measure surface moisture at the shift level
- Inspect deck open area after each wet shift
- Log the pressure drop across dust collection
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized lump and fines for smelting |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 260 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while drive and cooling margins determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.