Design basis for limestone contract crushing
The design basis starts with the rock, not the machine. Limestone is rated at 30–150 MPa compressive strength with low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.35 t/m³. Soft and non-abrasive enough for impact crushing in a single stage; clay seams and moisture are the usual complications. Indicative values are starting points for a design, not guarantees.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of 0–5, 5–20, 20–40 mm and ground filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Limestone · 30–150 MPa · abrasion low |
| Design throughput | 100 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | 0–5, 5–20, 20–40 mm and ground filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw or impact → screen → optional grinding mill |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a limestone contract crushing this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For limestone at 100 t/h the working train is jaw or impact → screen → optional grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for limestone and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 320 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 40% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–20, 20–40 mm and ground filler |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 320 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for limestone, while mobility and fast set-up determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.