Design basis for gypsum remote site
The design basis starts with the rock, not the machine. Gypsum is rated at 20–60 MPa compressive strength with very low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.25 t/m³. Soft and prone to caking; drying and air-flow control in the grinding circuit matter more than crushing force. Measurements are only comparable when the sieve standard is the same.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 70 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of ground powder, 0–10 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gypsum · 20–60 MPa · abrasion very low |
| Design throughput | 70 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | ground powder, 0–10 mm |
| Loose bulk density | 1.25 t/m³ |
| Suggested circuit | impact / hammer → screen → grinding mill |

Why unstable powder fineness appears in this circuit
D97 drifts even though the mill settings have not changed. In a gypsum remote site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- classifier rotor speed and system air flow are tuned independently
- duct leakage changes the real air volume
- feed moisture or top size varies between batches
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) sample D50 and D97 every hour for a full shift; 2) measure airflow at the mill outlet; 3) check bag-filter differential pressure. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For gypsum at 70 t/h the working train is impact / hammer → screen → grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gypsum and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~88 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.25 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 150 kW order-of-magnitude connected load |
The corrective actions for unstable powder fineness are applied on top of this base circuit: tune classifier speed and fan damper as one control loop; seal the ducting and verify air volume at the collector; stabilise feed size and moisture before the mill inlet.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 30% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Sample D50 and D97 every hour for a full shift
- Measure airflow at the mill outlet
- Check bag-filter differential pressure
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 70 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground powder, 0–10 mm |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 150 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gypsum, while energy and spares autonomy determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 70 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.