Design basis for marble remote site
The design basis starts with the rock, not the machine. Marble is rated at 50–120 MPa compressive strength with low abrasiveness, low moisture sensitivity and a loose bulk density around 1.40 t/m³. Valued for whiteness, so iron contamination and tramp metal protection matter more than reduction ratio. Operator notes from the first month are often the best diagnostic data.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of ground calcium carbonate, chips, aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Marble · 50–120 MPa · abrasion low |
| Design throughput | 110 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~650 mm |
| Target product | ground calcium carbonate, chips, aggregate |
| Loose bulk density | 1.40 t/m³ |
| Suggested circuit | jaw → impact → screen → grinding / classifier |

Why iron contamination and whiteness loss appears in this circuit
Brightness falls and dark specks appear in the finished filler. In a marble remote site this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- tramp iron passes the upstream magnet
- worn liners and grinding elements add metallic fines
- mild-steel ducting or a worn classifier rotor sheds scale
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) measure brightness on every finished batch; 2) test the magnet with a sample piece weekly; 3) inspect liners and rotor blades at each planned stop. HAMAC states nominal values alongside the conditions they were measured under.
Recommended equipment configuration
For marble at 110 t/h the working train is jaw → impact → screen → grinding / classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for marble and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.40 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 240 kW order-of-magnitude connected load |
The corrective actions for iron contamination and whiteness loss are applied on top of this base circuit: fit a magnetic separator and metal detector before the mill; select wear materials against the required brightness specification; inspect and line the conveying path for exposed steel.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Measure brightness on every finished batch
- Test the magnet with a sample piece weekly
- Inspect liners and rotor blades at each planned stop
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground calcium carbonate, chips, aggregate |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 240 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for marble, while energy and spares autonomy determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.